![]() |
By Rob Cochrane With additional research By Maryanna Schaefer 30th March 1990 |
|
Vesting Day marks the end of the CEGB after 32 years of service to the consumer. They were eventful years. We did not get everything right and no doubt, with hindsight, some things could have been done differently. On balance, however, I believe the CEGB did a good Job. |
||
Yours sincerely Gil Blackman Chairman, Central Electricity Published by the CEGB, Designed by Journalist Services,
|
![]() |
|
By 1881when Punch published this cartoon the baby created by Michael Faraday and others was beginning to be noticed. In that year, Godalming in Surrey had installed electric street lighting and King Steel and King Coal, the giants of the industrial revolution on which much of Britain's prosperity was built, were right to ask what this new industry would become. |
![]() |
|
Like Topsy, it just growed… |
||
| The 140 "selected stations" stayed in the ownership of the power companies and municipalities, but CEB engineers controlled generation using the most efficient plant to achieve the lowest production costs. That wasn't all. Because the inter-connected stations could "pool reserve plant" there were even bigger savings. The average cost of electricity was halved. One company was offering domestic lighting supplies on a' sliding scale from today's equivalent of 3p to 2p a unit, and power for cooking or domestic chores at half that — and the result was a new "electric revolution." For the first time ordinary people could afford electricity. Showrooms were hiring out cookers at six shillings (3 Op) a quarter. Industry was reaping equal benefits — thanks to the way more use could be made of stations with the best plant. |
|
![]() |
Weakened by war and with coal in short supply, the power system was ill-prepared for the big freeze of 1946/1947. Temperatures were below zero for long periods and even in central London they fell to as low as minus 15 degrees Centigrade. There were power cuts across the country. In February, with snow deep on the ground, members of the Central Electricity Board wearing overcoats and mufflers were photographed meeting by candlelight at the Board's London headquarters. |
Running the early grid had its problems. Control engineers were having to develop skills in forecasting likely demand in their area — learning the different effects of wet or dry washdays And the peaks that could occur if Gracie Fields was singing on the wireless. "Perhaps the biggest instance was when Tommy Farr fought Joe Louis for the world heavyweight boxing title in 1937. The fight was being broadcast at 4.0am our time with listeners having lights on, electric fires glowing and coffee percolators at full blast. We'd kept extra power stations on load and it was just as well. The normally low night load shot up by 400MW that night — a quite incredible increase/or those years." |
|
|
Boxer Tommy Farr . . . |
Another breakthrough came in 1938. Until then the grid had been operated in seven virtually independent systems. Having too many stations connected in one big network had been thought too risky, but when it was seen that the South of the country hadn't got enough generating plant to meet likely needs, while the North had capacity to spare, the experiment was tried — just for that winter. |
|
Control in “The Hole” |
![]() |
| Miracles take a little longer | |
The reorganised industry came into being on April 1, 1948 — and the new British Electricity Authority could have taken as their motto: "The impossible we do today — miracles take a little longer!" The situation was critical. Government restrictions and shortage of supplies meant that only a third of the new plant planned towards the end of the war had been commissioned. The BEA had inherited nearly 300 power stations, but a lot of the plant was over 25 years old with many sets generating less than 8MW. Even in summer there was a plant shortage because of the need for essential maintenance and overhaul, while a severe winter that year would have left the industry 1,650MW short. The future looked equally bleak. As the Authority told the Minister of Fuel and Power in their first annual report. "By Vesting Date it was clear that the situation, far from improving, was likely to deteriorate further." In the first year's operation there was only one crumb of comfort. Massive efforts by power station staff to keep the maximum amount of plant in operation plus the best possible use of the grid had halved the number of power cuts — to 79 occasions! |
|
Flying high |
|
The first priority was to get new plant into commission as quickly as possible. The size of generating units was limited by ministerial order to 30MW and 60MW sets, even though Battersea had installed a 105MW unit back in the 1930s. What mattered then was to have sets of proven reliability, and the strategy paid off — but there was another problem. It was no use providing plant without the means of delivering the power supplies. The original grid had served the country well, but to meet the future needs the carrying capacity would have to be doubled. Rather than festoon the country like a spider's web with more 132kV lines, the BEA decided to build a supergrid network of 275kV lines, each able to carry six times the power. Not only that. The lines were to be capable of modification to operate at 400kV. All in all it was a formidable engineering programme, but that was only part of the problem facing the new authority. They had to create an organisation that would work effectively. The men at the top couldn't have come from more different backgrounds. The Chairman, Lord Citrine, had been General Secretary of the TUC. His deputies were John (later Sir John) Hacking, Chief Engineer of the CEB who now took over operations, and Sir Henry Self, from the Civil Service who headed the administrative side. The headquarters staff were spread between a number of premises. At first the main administrative HQ was at Generation House — a rabbit-warren of a place in Great Portland Street, with others in Winsley Street (above the Waring and Gillows store) and in Trafalgar Buildings. They had plenty on their hands, having to cope with their own functions and at the same time devise ground rules for the future. Meanwhile the day-to-day job of running the industry was carried out in the 14 operational Divisions which had been set up. The Divisional Controllers of those days — senior people from the private power companies and municipal undertakings — were pretty well autonomous. It was probably as well, because their job was anything but easy, especially at first. As one newcomer to the industry in 1948 recalls: "Our Divisional Headquarters was a Victorian terraced house with a total staff of only 50 people, dealing with the operation of 23 stations (including a couple of hydro’s and one station with diesels from a captured U-Boat); maintaining and operating the grid; planning for and supervising the construction of new stations and the supergrid, including the way leaving; as well as coping with the purchasing, administrative, personnel and accountancy functions." |
|
![]() |
In the early days of nationalisation many of the headquarters of the new Divisions were installed in what had once been private homes. They were on a domestic scale, very different to the regional headquarters that the CEGB was later to build. The contrast can be seen by comparing the White House (left) at Cockfosters with Beckwith Knowle (below left), headquarters of the later North East Region at Harrogate, Yorkshire, and Sudbusy House (below right), the Board's London headquarters near St Paul's Cathedral. |
|
![]() |
![]() |
|
That was only part of the job. Those Controllers had to weld together staff from jealously independent power companies and municipal undertakings plus the CEB, all with their different practices. Old loyalties and rivalries weren't easy to eradicate. One manager was heard to remark: "You'll get nowhere in this industry unless you have CEGB tattooed on your backside”. |
||
The effect of nationalisation was felt right down the line. A past power station manager recalls how at first there was a great deal of trepidation. "We had always felt that our company was superior to any of the others, but the giants whose coat tails we had been grabbing were disappearing to better jobs. The chaps on the floor were afraid all their earlier bonus payments would be disappearing too. But we soon found there were advantages, and not just because there were jobs up for grabs. We had always been run on a very tight budget, but now there seemed to be plenty of money for spare plant or anything else we thought we needed. The stores had never grown so fast!" By the mid-1950s the new industry had got well into its stride. Good progress was being made towards the targets the BEA had set. Although demand was rising rapidly, power cuts were a thing of the past. A massive amount of new plant had been built, 8,000Mw, a two-thirds increase. The first 40-mile section of 275kV supergrid was already in operation, with another 1,500 miles of 132kV and 275kV line under
construction. There was some concern about the adequacy of future coal supplies, but against that the prospects of economic oil-firing were looking more promising. What's more, there was the promise of nuclear power to come, heralded by the press as a guarantee of a cheap energy future. The BEA's pre dictions on that score were more cautious, but with a diversity of fuels be coming available the outlook was good. It could have seemed an obvious case for leaving well alone as far as the organisation of the industry was concerned. But it didn't work that way. In quick succession there were two major changes. A new South of Scot land Electricity Board was set up with responsibility for both generation and distribution in that area. The BEA was renamed the Central Electricity Authority — and as an experiment in streamlining its own organisation, the North Western Division was merged with the Merseyside and North Wales Division. It showed the shape of things to come. But a much bigger shake-up was in the offing. The Scottish change had been a political decision, but the sniping hadn't stopped there. In 1954 the Herbert Committee had been set up "to enquire into the organisation and efficiency" of the whole industry in England and Wales. Relationships between the BEA and the Area Boards hadn't always been happy. Now many of those Boards seized the chance to criticise what they saw as over-centralisation and the way the BEA had exercised responsibility as the policy making Central Authority. The result came in 1958. A separate Electricity Council was formed to coordinate policy for the industry as a whole. The Central Electricity Authority disappeared and in its place was a new Central Electricity Generating Board, still the industry's "manufacturer and wholesaler" with the task of achieving the most economic generation possible and delivering power supplies in bulk to the Area Boards for distribution to consumers. It was a job that would give the CEGB and its staff more than enough to think about for the next 30 years. |
||
Evolution, not revolution The prospects were exciting. There was no doubt that the staff could meet the challenge. The first priority was to make sure they were organised in the best way to do it. |
||
|
||
![]() |
The CEGB's first nuclear power stations were Berkeley and Bradwell. Berkeley (left), on the eastern bank of the Severn Estuary was officially opened in April, 1963, by the Duke of Edinburgh — at the same moment as a similar ceremony was performed at Bradwell in Essex. |
|
Staff felt much the same, and the new Board recognised this. One of its members was Andrew Cooper who realised the importance of the personnel function, especially now that Labour Relations had become a responsibility of the Electricity Council. A separate Personnel Department was formed under his aegis as Member for Operations and Personnel, and he didn't hesitate to make his views known — to the Board and staff. |
||
"In the new organisation we shall certainly achieve the targets we have set ourselves: but we have learned enough from past experience to know that this can be done by controlled evolution far better than it can be by painful revolution." |
||
![]() |
Bradwell nuclear power station was built on the south east extremity of the Blackwater estuary in Essex. The site was originally a marsh, below the high tide level, so all land in the vicinity of the main buildings had to be raised. |
|
And as Power News reported in 1962: |
||
Prince’s sticky situation |
||
Crisis amid the winter snows |
||
![]() |
NO ONE involved "at the sharp end", transmission engineers, linesmen, station staff or grid control engineers — is likely to forget the start of 1963. The New Year came in with gales and a blizzard... heavy, driving snow with temperatures plummeting to minus 15 degrees C even in the daytime. Grid lines sagged and broke under the weight of ice, with line gangs staggering through snowdrifts to make repairs. |
|
|
||
Coal stocks were frozen to a depth of two feet. Fires were lit under coal trucks so they could be emptied. Frozen jetties were a hazard for staff un- loading colliers. Even so they managed to generate the supplies needed until January 24 when — for the only time that winter — there wasn't enough plant to meet the demand. For periods of 10 minutes to an hour there were widespread disconnections. But worse was to come. The next night the grid faced the worst disruption in its history. |
![]() |
|
Heavy fogs in December had polluted insulators and substation equipment with industrial dirt. A slight thaw during the day was followed by a quick freeze — and the trouble started. That night there were 700 flashovers on lines and electrical equipment. Grid control engineers could see the possibility of the grid being split, with some areas not having sufficient generation to meet the load. Phone calls warned stations to restart plant that had been shut down for the night. But as the morning demand grew and flashing lights on wall circuit diagrams showed that switches had "tripped out" the emergency procedures were implemented. Instructions were given to "shed load"... stage by more severe stage so as to safeguard the grid from total collapse. The situation was becoming critical — though they still didn't know just how critical it would get. Many stations were isolated from the grid. As the morning demand grew, widespread disconnections were inevitable — in some areas up to a fifth of normal consumption. The worst hit part was the south of the country which had been relying on the grid lines from the Midlands, but one by one these failed. Stations which had become disconnected were trying t( get supplies flowing again, sometime; by highly unorthodox means. A West Thurrock engineer remembers: "We'd had to shut down completely when we got isolated from the grid. So there we were, huddled round a paraffin heater in the Charge Engineer's office, trying to puzzle out some way to get rid of the ice on the station bus- bars (heavy metal conductors) because until that was done there was no way to restart the plant. |
||
![]() |
It only takes a spell of bad weather to remind everyone that it can be a tough job at the sharp end of power generation. The winter of 1962/63 was one to remember. It was marked by Arctic conditions with gales and blizzards, with temperatures plummeting to minus 15 degrees Centigrade in daytime. At power stations it was cold enough to freeze the curtain of water at the foot of cooling towers, restricting air flow — leaving staff the job of smashing a way through the wall of ice. Thick layers of ice had to be patiently chipped away when external valves needed adjusting. Coal stocks were frozen to a depth of two feet. Coal wagons froze, making them difficult if not impossible to unload. Frozen jetties were a hazard for staff unloading colliers. |
|
![]() |
For some staff in the transmission districts the conditions were even tougher. Frozen insulators had to be cleared by hand and that meant climbing ice-coated transmission towers. Teams called out to damaged lines in exposed areas like the Pennines faced snow driven by gale force winds in their efforts to keep the power flowing. |
|
Even putting braziers under the busbars hadn't worked, and every time we tried to bring in supplies from another station the circuits just tripped out again. Eventually we managed it by defeating the automatic electrical protection systems and feeding in supplies, so that the permanent short circuit would generate enough heat to melt the ice." |
||
Before the night was out, the grid was being operated in four separate groups. Crisis point came at 9.0 am when engineers in the National Control room gave the instruction "Shed Stage 6 — and quick." This was the most desperate step ever taken to safe-guard the system. The message was transmitted to three separate parts of the country and passed on to Area Board engineers who in turn opened switches to disconnect sufficient sup-plies to avoid potential disaster — all within the space of 60 seconds. |
||
The Pattern for development |
||
![]() |
Big power stations are big users of coal. A 2,000 megawatt power station can burn six million tonnes or more of coal a year. Transport was recognised as a major problem and the solution was the merry-go-round system with trains shuttling between pit and power station. This train at Ratcliffe power station, near Nottingham, has just dropped its 1,000 tonnes of coal into ground hoppers as it moved slowly through the unloading house before returning to the colliery |
|
|
![]() |
||
"When you see those same turbines nowadays they are smothered in instrumentation which wasn't there when we first ran the plant. In the same way, we looked for quality assurance on things like boiler welds and made sure the right materials were used. A lot of work was done in the Marchwood and Leatherhead laboratories. There were enormous problems in getting things right. |
||
![]() |
The enormous changes that 40 years of development brought to the electricity supply industry are graphically illustrated by these two turbines. On the left, a steam turbine on its way to Barton power station, Manchester, in the 1930s |
|
|
![]() |
|
Getting the plant right took another 10 years and a lot of effort all round. But as Gil Blackman added: "With that knowledge and experience in our locker, we now have some of the best plant operating anywhere in the world." |
Even in those latter 1960s the picture was anything but doom and gloom. The CEGB's policy of siting big coal-fired and oil-fired station close to their fuel sources was being proved right. Generating costs were being cut still further. And by the there had been developments in the nuclear fields. |
This green and pleasant land |
FROM early days the industry had 1 recognised that the environment (mattered. It showed in the care the CEB took over the design of the original grid transmission towers. On nationalisation, the BEA had ' decided that the architectural de-sign of new stations would be submitted to the Royal Fine Art Com-mission. But when the CEGB was created, it was put under a statutory duty to "preserve amenity" and Hinton was under no illusion concerning the way people felt about lines — or stations. But since 1947, planning permission was needed as well, with district and county planning officers often having very different views about where the line should go. As one wayleave officer said when he was discussing a line route near Hadrian's Wall: "It's a good job Hadrian wasn't around now ... he'd never had got planning permission for all that lot!" |
![]() |
Modem power stations are among the biggest things created by man so they can never be completely hidden. But their outlines can be softened by judicious planting (left). Nature trails (right) and reserves have also been established at many stations. |
![]() |
There was one inevitable question: "Why can't the line be put underground?" This was considered whenever lines were being routed through sensitive areas like beauty spots. What ruled it out other than in exceptional cases was the heavy extra expense. |
||
|
Power Station in a mountain |
|
![]() |
Imagine excavating a cavern big enough to take St Paul's Cathedral, linked to the surface by tunnels you could drive a bus down. That is the measure of Dinorwig, the "CEGB's" power station in a mountain" that lies hidden beneath the beauty of Snowdonia. Dinorwig is a pumped storage station. At night when generating costs are low, it takes electricity from the grid to pump water from its lower lake, Llyn Peris, to Marchlyn Mawr, its upper reservoir. During the day the water can flow back, providing power for the grid. The station is the National Grid's pacemaker, helping to ensure that the electricity supply is both regular and steady. Almost every aspect of its construction deserves a place in the record books. The scheme was the largest of its type in Europe. At £425 million it was the largest civil engineering contract ever announced in the UK. In all some two million cubic metres of concrete was poured — enough to fill Wembley Stadium to a depth of 100 feet. |
|
![]() |
Why was it built inside the mountain? |
![]() |
AS the CEGB went into the 1970s, the future looked bright. Demand was still growing steadily. More 2,OOOMW stations were coming into service and so were gas turbine stations using aero-type engines which could be brought into operation very speedily to help cope with daily peaks and unexpected surges in demand. Some 1,300 miles of400kV line had already been built. Within the next few years much of the 1,500 miles of 275kV supergrid would be modified for operation at 400kV. |
||
"Station maintenance staff were doing a good job. But it seemed silly to me that often they were sitting on their hands from Monday to Friday when the plant was running, then having to come in at weekends to carry out the maintenance work ... in effect condemned to a seven-day week. There were similar problems on the transmission side. The answer was to bring in work-stagger arrangements together with an incentives scheme which would give them a third extra pay and a reduction of overtime to as near zero as we could make it |
||
The idea was sound. It enabled the CEGB to take on the massive amount of new plant without a massive increase in numbers. Manpower productivity shot up. But the job of implementing the scheme at each location and selling it to the workforce was yet one more headache for managers. |
||
Overhead line working is no job for the fainthearted as the photograph below demonstrates. |
||
The nature of the job had developed since the CEGB was set up, but the organisation hadn't changed with it. That came in the early seventies. Stations had always been able to call on Regional Scientific Services Departments where corrosion and similar problems were beyond the scope of station staff. Investigations leading to improved methods of operation had reduced failures of boiler tubes and other plant. Welds had caused problems, and non-destructive techniques were developed for testing them. Now Regional Engineering Departments were formed to help stations cope with problems of an engineering nature, and to provide teams to assist in the commissioning of new plant. |
||
![]() |
Construction of the 2000MW link between Britain and France involved robot machines with more than a touch of science fiction about them. Each country was responsible for installing two of the four pairs of cables in what was nicknamed "Le Link" by Power News. To protect them from damage, the cables had to be buried in trenches beneath the seabed. To install their cables, the British developed two robot machines that would have looked at home in a science fiction magazine. |
![]() |
The first was the trench cutter (above left), a 175-tonne underwater tractor which crawled along the seabed. It was controlled by an umbilical cord from a barge on the surface above. In some 12 weeks it twice cut its way along the seabed the 31 miles from Folkestone to Calais, removing more than 200,000 tonnes of chalk, rock, and clay and laying a steel guiding hawser in each trench. |
||
New men with new ideas were taking over, and the effects were being felt all down the line, especially as more and more Directives and Procedures descended from Board Headquarters covering everything from changes in management concepts to new and detailed procedures like those governing contract and purchasing requirements. |
![]() |
The train now standing |
![]() |
WHAT are nice trains like you doing in stations like these? That question could be prompted by both these photographs. The trains, or to be precise the diesel electric locos, are pictured running fast but standing still in a power station. They were an innovative temporary solution to a rare but often time-consuming technical fault on a generator-exciter failure. The exciter provides the current for a main generator's field coils. Without the current there is no output from the generator. The idea was demonstrated at Willington power station in 1968 when the armature on one of B station's 200MW units failed. While repairs were completed, the station hired a loco whose electric output was just what the generator wanted, the loco ran for 300 hours and the unit maintained full output. Other power stations tried the same solution when they faced an exciter problem. |
||
Ever since the thirties, engineers in grid control centres had been forecasting likely demand and selecting the most economic plant to meet requirements. In some ways the job had be-come easier. Computers in National Control could give up-to-the-minute information on the running costs of every generating unit in the country. But engineers still had to decide how much plant was needed to meet a demand that changes day by day and minute by minute. Insufficient plant would mean power cuts. Too much would waste fuel. Gas turbine stations had made a big difference. They weren't cheap to run, but they could be brought into operation at the flick of a switch. Soon there would be another source of ready power. A pumped-storage station, the largest in Europe was under construction at Dinorwig in Snowdonia. This would be able to provide 1,300MW of power within 10 seconds and its full output (1,800MW) in less than two minutes. It would prove a major help in operating a system that was getting still more complex. |
||
From "pea soup" to marine biology |
||
"THERE'S a war on - we've no time for research now." That was said by the CEGB's Chief Engineer on the day war was declared in 1939. It was a natural reaction, but it doesn't reflect the part that research has played in the industry since the 1930s. |
||
![]() |
Probe in hand an acid-rain researcher works inside a climate-controlled "solar dome" greenhouse at the Central Electricity Research Laboratories at Leather-head. |
|
But research requirements were growing rapidly, especially as the first nuclear programme was started. Leatherhead was extended and new laboratories were built at Marchwood and Berkeley. The range and extent of work was enormous. On the nuclear side alone, the Berkeley laboratories were dealing with a massive programme including work on corrosion inside reactors. |
||
![]() |
Research was always the hidden side of the electricity supply industry. At peak the CEGB had up to 3,000 staff working on a bewildering variety of issues from nuclear physics to fish populations, reaction kinetics of burning coal to aerodynamics |
![]() |
Since 1954 research staff have been involved in a very large environmental programme. Again the range of activities has varied greatly. One problem coal-fired stations faced was the disposal of pulverised fuel ash. Development work has enabled PFA to be used in building materials. Crops have been grown in areas filled with the ash. Marine and freshwater biology have played a considerable part, from preventing mussels fouling the pipes supplying coastal stations with cooling water to the culture of fish in the warm water outflows. |
||
Keeping the lights burning The late seventies brought fresh problems. As a worldwide depression hit this country the CEGB was faced with an unprecedented situation. The demand for electricity fell, and it was to stay below the 1978 level for an-other six years. The Chairman, Glyn England, had visited the United States to see what was being done in that field. "I found that President Carter's people heading the alternative energy project were being very heavily funded by British standards, and came back with the clear view that we ought to be doing more in terms of practical experiments. As a direct result, the first wind machine was built at Carmarthen Bay, and I put British manufacturers on notice that, if it was successful, we would be in the market for wind turbines" The CEGB's first wind turbine, in-stalled in 1982 at Carmarthen Bay, in South Wales, had an output of 200 kilowatts, enough for a small village. Later other, larger, machines were tested on the site. A much larger, one MW turbine, was commissioned at Richborough in Kent in 1989. Application was made for a wind park at Capel Cynon in Dyfed, Wales, with 25 wind turbines each with an output of 300 kilowatts. Two other sites with potential as wind parks were identified, in Cornwall and the North Pennines. But useful as alternative energy sources might prove, in the latter seventies it was believed that they wouldn't be enough to meet a resumed growth in electricity demand and the need to replace older stations.
|
||
![]() |
The energy crises of the 70s raised interest in renewable energy sources such as wind, waves and tides. Interest was heightened in the 80s with growing public concern over environmental matters |
![]() |
By the turn of the century the first generation of nuclear (magnox) stations would be shutting down. The Board was convinced that proposals for future stations should include a sizeable proportion of nuclear plant. |
||
![]() |
The main headline in Power News caught the flavour of the Board's response to the miners' strike. The CEGB's job was to keep the lights on, not to take sides in the dispute. |
|
The Conservative Government which followed was even more committed to nuclear power. In 1982 they appointed Walter Marshall, then Chairman of the Atomic Energy Authority, as the new Chairman of the CEGB. But the Board knew they would have a hard fight on their hands before they got final approval to build Sizewell B. |
||
![]() |
Silhouetted against the night sky even an ash conveyor can acquire a certain beauty ... as this plant at Drax demonstrates. |
System Operations used computer simulations to guide the operation of plant and get every last ounce of benefit from the fuel supplies available. Oil supplies were purchased on a vast scale in a way intended to minimise the visibility of the operation from price escalation and other factors. It entailed bringing oil in from different parts of the world by ships of many nationalities so as not to risk price rises if the extent of purchases became known. |
|
![]() |
As public inquiries go, the Sizewell one, into the CEGB's plans to build a pressurised water reactor on the Suffolk coast was memorable for its length rather than its intrinsic interest. True, its start on - January 11, 1983, was marked by a demo and a Press conference, as was its final day on March 7, 1985. But they were very much the highlights. In between there were 340 days of hearing, a British record, at which 200 witnesses gave a total of 16 million words of evidence. It was equivalent; it was calculated, to 24 copies of War and Peace. The average reader would doubtless have found that by contrast with the inquiry transcript Tolstoy's blockbuster of the Napoleonic wars was fast-moving, even racy. |
The power cuts due to the miners' strikes of 1972 and 1973 caused great inconvenience and discomfort in homes and cost industry dear. The effects would have been far worse if nuclear stations hadn't been providing supplies. |
|
![]() |
A spectacular demonstration of the safety of transporting spent nuclear fuel by rail from nuclear power stations for reprocessing was held in 1984. Watched by millions on television, a heavy diesel locomotive pulling three passenger carriages was driven at 100 miles an hour into a nuclear fuel flask as it lay on the test track at Old Dalby in Leicestershire. The loco was crushed but the flask remained intact. |
At the public inquiry into the Sizewell B proposal, every aspect was examined exhaustively. Then after the inquiry finished, but before the report was issued, came the Chernobyl disaster. |
|
Death…and reincarnation |
![]() |
|
THE Government's decision to privatise the electricity supply industry was one of the measures included in the Queen's Speech to Parliament in 1987, though the way it would be done wasn't spelled out until the 1988 White Paper. That envisaged the CEGB's generating responsibilities and assets being split between two new companies, National Power and PowerGen, the larger of which (National Power) would inherit 70 per cent of the power stations, including the nuclear plant. The grid would retain its central role in scheduling and directing the use of power stations but it would be owned and operated by a grid company which itself would be owned by the 12 distribution companie - formerly the Area Boards. |
||
There have been only six chairmen of the CEGB. The first was Sir Christopher Hinton, later Lord Hinton, served from 1957 to 1964, Sir Stanley Brown served from 1965 to 1972, Sir Arthur Hawkins from 1972 to 1977, Glyn England from 1977 to 1982, and Lord Marshall from 1982 to 1989. Gil Blackman was appointed Chairman in January this year. |
||
![]() Sir Christopher Hinton |
![]() Sir Stanley Brown |
![]() Sir Arthur Hawkins |
![]() Glyn England |
![]() Lord Marshall |
![]() Gil Blackman |
Clearly a difficult road lay ahead, and the Generating Board took a positive view. As Walter Marshall - now Lord Marshall, explained: "We thought it better if we handled the change ourselves, anticipating theirlegislation by dividing into three Divisions. And that's what we did." |
For the Record |
In November, 1989, the Government announced that the AGRs and Sizewell B PWR station would also remain in the public sector, and that no further PWRs would be built until the situation was reviewed in 1994. To Lord Marshall in particular the announcement came as a blow. He felt unable to accept the Government's decision and resigned, and Gil Blackman was appointed the last Chairman of the CEGB. And that says it all. |
![]() |