Introduction |
|
|
| BIyth
Power Station is situated at Cambois in Northumberland on the northern
bank of the River BIyth between the tidal estuary and the North
Sea.
The site comprises two stations, BIyth 'A' and BIyth 'B', with a
combined generating capacity of 1180 megawatts. |
The
241 acre site is divided by the Bedlington-Cambois road. The coal
handling installations lie to the north side of the road and the
two main station buildings to the southside.
The increasing demand for power in the immediate post-wa^period
led to the then existing North Eastern stations, of Dunston and
North Tees, being extended and new stations being built on the Tyne
at Stella North and South.
The plant installed in these stations was of relatively small output
but of well proven design, to enable the demand for power to be
met quickly.
Biyth saw the dawn of the new era in power station design and technology
with the installation of larger and more efficient plant. It was
initially planned to build a station containing 6 x 100MW turbo-
generators. This was changed to suit new advances made in design,
first to 6 x 120MW units and then finally to 4 x 120MW units with
a'B'Station containing 2 x 275MW units and 2 x 350MW units.
Ministerial consent was given for the building of the 'A' Station
in February 1955 and all units were commissioned by June 1960. The
four "B" Station units were installednd commissioned by
September 1966.
At the times of their installation both 'A' Station Unit 1 and 'B'
Station Unit 5 were the largest in ' the country. The 2x275MW units
(5&6) on 'B' Station were decommissioned on grounds of economy
in 1991. |
|
Blyth ‘A’
|
Blyth ‘B’ |
 |
 |
|
|
| |
|
| |
Power stations and the grid
|
 |
More
than 50 years ago the interconnected grid system first linked power
stations and local areas so that they could help each other over
difficult periods and transfer energy when it was economical to
do so.
During the 1939-45 War the role of the grid changed from an area
to a national facility and electricity was first transmitted over
long distances.
The National Grid Control Centre, works through four area grid control
centres. It arranges for plant in power stations to be run in the
most economic order possible to meet the constantly changing demand
and is also responsible for the operation of the grid system, which
is the largest in the world. |
National
Power at present uses coal, oil, gas, water or wind power as fuel.
Its power stations range in size from small hydro-electric units
to the largest coal-fired plant in Western Europe.
National Power competes with other generating companies and sells
almost all of its output through the new wholesale market for electricity,
called 'the pool' It has contracts to supply its main customers,
the twelve regional electricity companies of England and Wales with
nearly 90 of its output.
As well as its main customers, National Power has contracts to supply
electricity directly to large consumers |
| Back to Top |
Below:
National Power's Energy Management Centre bids into the electricity
'pool |
Above : National Grid Control
Centre
|
The
functions of this transmission grid are:
To interconnect power stations and cut down the amount of reserve
plant needed nationally.
To make most use of stations with the lowest costs.
To transfer power from one part of the country to the other.
The National Grid Company is responsible for almost eleven thousand
miles of overhead grid lines.
Producing almost half of the electricity for England and Wales,
National Power is one of the largest privately owned generating
companies in the world. Its aim is to become the best. |
 |
| |
Civil engineering work |
|
A
layer of strong boulder clay, about 70ft thick overlying sandstone
and coaj provides a bearing medium amply capable of supporting the
station.
The main foundations are spread to load the clay to about 2.3 tonne
per square foot, adjustments having been made according to the depth,
size and shape of individual foundations.
The 'A; Station turbine hall is 394ft long by 122ft wide by 85ft
high and is constructed of reinforced concrete frames clad with
brickwork. The boiler house (362ft long by 93ft wide by 157ft high)
is of steel frame construction with aluminium cladding.
The main buildings of the 'B' Station comprise a 675ft long by 166ft
wide by 100ft high turbine hall and a boiler house, which is the
same length but 105ft wide by 170ft high. Both are of steelframed
construction, clad with aluminium and glazed. The roofs are of lightweight
aluminium decking. The combined volumes of the main buildings represent
27cu ft/KW of installed capacity compared with 26.3 cu ft/KW for
the 'A- Staion.
There are two 450ft and two 550ft high chimneys serving the 'A'
and 'B' boiler houses respectively |
 |
|
| |
Coal Handling |
|
The
coal handling equipment installed at BIyth consists of conveyor
systems integrated to feed both stations as necessary. The consumption
of coal averages 51,000 tonnes per week, rising to 70,000 tonnes
per week during thewinter. In the summer months, when the electricity
demand is low, much of the coal supplied to the station is delivered
to stock. This gives a suitable reserve supply which can be fed
to the power station using the reclaim conveyors.
The provision of new "Merry-Go-Round" (MGR) facilities
became necessary in 1981 to accept the new high capacity rapid discharge
(NBA) wagons adopted by British Rail for the North East railtransport
system.
The new coal handling equipment was designed to accept all coal
deliveries by rail. Each train consists of thirty-six HBA wagons
each of 45 tonnes gross weight. The system provides for each train,
carrying approximately 1100 tonnes of coal, to be emptied within
sixty minutes.
Limitations imposed by the site boundaries determined that the new
facility could not be in the form of a conventional MGR loop which
would have allowed the continuous movement of trains. Instead the
train arrives on site and pulls onto a reception track. The locomotiveuncouples,
runs around the wagons, recouples at the opposite end, then slowly
moves over the unloading track hopper and discharges the coal before
eventually leaving site. |
Coal delivery
by train |
|
 |
|
| Coal stock handling equipment (Terex) |
|
|
A
Station Boiler Plant |
Coal
is elevated from the coal handling plant by conveyor systems. A
travelling distributor transfers the fuel from the last conveyor
belt into the four station bunkers, each of which has a capacity
of 2000 tonnes |
After
pulverising, the coal is transferred by an air stream to the burners.
This air is provided by the primary air fan associated with each
mill.
To permit the heat release from the fuel to follow the steam requirements
of the generating sets, the raw coal is fed into the mills by rotary
table feeders. These are driven by constant speed motors through
variable gearboxes, the speeds of which are regulated by the automatic
control system.
Each of the four Babcock - Wilcox boilers has twenty, 26 inch diameter
horizontal flame, circular type burners feeding pulverised fuel
(P.F) into the furnace. In addition there are twelve pressure-atomised
oil burners, with automatic propane ignition. These burners, used
for starting up purposes and maintaining flame stability, are operated
remotely from the unit control room. The oil is stored iin two 10,000
tonne storage tanks, and is heated before being sprayed into the
furnace at a pressure of about 550 p.s.i.
Under full load conditions each boiler is capable of evaporating
continuously 860,000 pounds of water per hour and converting it
into steam at a pressure of 1,600 p.s.i. at a temperature of 543°C.
The inlet water temperature under these conditions is 230°C,
heat having been obtained from the feed water heating system associated
with each turbine. Additional heat is taken from the flue gases
by means of low temperature, high temperature, and topping economisers. |
The
radiant furnace has a volume of 86,000 cubic feet and the steam
raising area of the water walls and boiler tubes is 16,750 square
feet. These tubes are 3 inches outside diameter with 0.348 inches
wall thickness. Steam leaves the boiler drum and passes through
three banks of superheaters where its temperature is further increased.
The Primary Superheater with a surface area of 18,875 square feet,
has a horizontal inlet section and a pendant outlet section. It
receives convected heat from the flue gases leaving the secondary
superheater zones. |
| Coal
pulverising mill |
 |

Boiler Drum
|
From the bunkers
the coal descends to the pulverising mills where it is ground to
a fine powder. There are five mills for each boiler, each of which
is individually driven by a 160 h.p. induction motor. Each mill
can handle up to 15 tonnes of coal per hour and four mills are sufficient
to maintain the boiler at full output. It is therefore possible,
under normal circumstances, to keep one mill in reserve or under
maintenance. |
| Back to Top |
|
|
The
Radiant Superheater, having a surface area of 3700 square feet,
receives convected heat from gases leaving the furnace and radiant
heat from the P.F. flames.
The pendant Secondary Superheater has a surface area of 15,000 square
feet. This receives convected heat from the furnace gases and raises
the steam temperature to 543°C before it passes to the turbine.
IIn the rear gas pass of the boiler, adjacent to the Primary Superheater,
is the Reheater which has an effective heating area of 41.900 square
feet.
In conformity with modern practice a reheat cycle has been adopted,
whereby the steam having expanded partially through the turbine,
is returned to the boiler to receive more energy in the form of
heat before being returned to the turbine for further expansion |
Development
of the reheat cycle was pioneered in the North East of England at
Blaydon Power Station in 1916 and at North Tees A Power Station
in 1919. Operational experience was gained between 1933 and 1950
on the reheat plant installed at Dunston B Power Station .
The reheat steam entering the boiler is at a pressure of 422 p.s.i.
and is heated from 369°C to 541 °C before returning to the
turbine. The hot gases can be prevented from passing through the
reheater and the primary superheater by means of ganged dampers
which divert the gases, so providing regulation of both superheat
and reheat steam temperatures. |
Spray
type desuperheaters give a fine adjustment of superheat temperature
to within ± 8°C and spray type desuperheaters are also
provided for emergency control of the reheat temperature.
Each boiler is equipped with automatic boiler control. Variations
in main steam pressure are detected and transmitted to the forced
draught (FD) fans and pulverising mills causing the necessary change
in fuel and combustion air to be made to maintain the boiler output.
A change in the air condition alters the pressure in the combustion
chamber; This pressure change is used to control the induced draught
(ID) fans.
Further automatic controls are used to maintain the correct temperatures
of superheated and reheated steam, and to keep a constant water
level in the boiler drum. |
 |
Each
boiler has two FD fans, driven by 370 horsepower 3.3kV motors, operating
at 730 rpm. These fans are mounted at ground level and take in warm
air from the top of the boiler house at the rate of 145,000 cu ft/min.
The air is passed through a horizontal tubular air heater, where
it takes in additional heat from the flue gases before passing to
the boiler. The two I.D. fans are driven by two-speed (730/585 rpm)
motors, each of 800/435 hp and 3.3kV. Each .fan extracts gases at
a maximum rate of 225,000 cu ft/min at 132°C. Both FD and ID
fans have radial inlet vane control.
Dust is extracted from the flue gases by cellular dust collectors
and electrostatic precipitators, with a - combined efficiency of
99.3. |
|
| |
| |
| |
| |
Boiler Burners |
|
|
| |
Turbogenerators |
|
The four Metropolitan
Vickers,120MW, 3,000 rpm turbogenerators are operated on the unit
principle of combining a boiler, turbogenerator and their principal
auxiliaries as a single operating unit. There are thus no connections
between the separate units, the only common services being those
of the station transformer supplies used for starting up purposes,
circulating water, town water and treated make-up water.
The turbines are of impulse design and have three, in- line, single
casing cylinders. The high pressure (H.P.) and intermediate pressure
(I.P.) cylinders are arranged in contraflow to balance out residual
thrust and the low pressure (L.P.) cylinder is of double flow construction.
To keep the length of the machine to a minimum, the 'close coupled'
technique has been adopted and the three shafts, which are solidly
connected, are supported on four bearings only. |
Steam at turbine
stop valve conditions of 1500 p.s.i. and 538°C passes via loop
pipes to the admission belt of the H.P. cylinder and expands towards
the governor end through a velocity compounded stage and eight impulse
stages before leaving the H.P. cylinder and returning to the boiler
for reheating. Bled steam for No. 6 feedwater heater is tapped from
the H.P. turbine exhaust pipework.
After reheating, steam enters the I.P. cylinder through two interceptorvalve
chests and loop pipes, expanding towards the alternator through
thirteen irrapuls® stages. Steam for Nos. 5 and 4 fee'dwater
headers i^bte* after four and eight re^ectWIywthstea'm for the No.
3 d'ea&Rator heater being taken from the I.P. exhaust.
Steam entering the L.P. cylinder divides into two flows and exhausts
to the condenser after expanding through six stages.
The final two stages of each flow form 'Baumann multi exhausts'
which give an increased exhaust annulus area for a given blade length.
Bled steam for Nos. 2 and 1 feedwater heaters is taken after stages
1 and 3 of each flow respectively. |
The
guaranteed steam and heat consumptions of the turbogenerators are
6.726 Ib/kWh and 8.232 BTU/kWh, respectively.
The hydrogen cooled alternators generate at 13.8kV and have an outpupt
of 120MW at 0.8 power factor with a hydrogen pressure of 30 p.s.i.
Four coolers, embodied in the stator casing, transfer the heat in
the hydrogen to a distilled water circuit, and the distilled water
is in turn cooled by heat exchangers which transfer the heat to
the main circulating water system.
Excitation is provided by gear driven, air cooled, pilot and main
exciters running at 991 rpm. To enable the exciter to have a short
time response to voltage changes, an amplidyne system has been used
which forces the field of the main exciter as required by the automatic
voltage regulator. Manual control of excitation is provided by a
field rheostat. |
 |
’A’
Station turbine hall |
|
|
| |
Condensing
& feedwater systems |
|
The
steam from the turbine exhaust is converted back into water in the
condenser, and in so doing produces a vacuum which lowers the "back
pressure" of the turbine thus increasing the efficiency and
output of the machine.
The condensers are of twin, two-pass design and with a total cooling
surface of 70,000 square feet. They are designed to give a vacuum
of 28.9 inches of mercury when supplied with 3,420,000 gallons of
water per hour at a temperature of 11.7°C.
Condensed water is extracted by two, 100 per cent duty pumps and
air is removed by three Leblanc type motor-drive rotary air pumps.
After extraction, the water passes through a drains cooler and then
through the first low-pressure feed water heater, where steam bled
off the low pressure stages of the turbine expansion adds more heat |
t
then passes through a gland heater, where waste steam leaking along
the labyrinth glands on the shaft gives up heat, through the second
low pressure heater and finally enters the combined deaerator heater.
Here, in addition to receiving more bled steam heat, the water is
cleared of entrained air and gases.
The outlet of the deaerator connects to the suction of two 100 per
cent duty booster feed pumps which are driven by 850 horsepower,
1500 rpm, 3.3kV motors. The booster pump discharge is then passed
through three high pressure feed water heaters to the two 100 per
cent duty main feed pumps which are driven by 2650 horsepower, 300
rpm 3.3kV motors. |
Although
the booster and main feed pump motors are started together from
one circuit breaker, the design is such that the booster pumps are
up to speed before the main pumps and a positive water pressure
is maintained at the main pump inlet.
After leaving the main pumps the water passes into the boiler drum
via the economiser |
 |
| Back to Top |
|
Main
feed pumps |
 |
Make-up
for the boiler feed water system is obtained from the town's mains
through a demineralisation plant. In this plant, organic matter
is first removed by flocculation and pressure filtration. The filtered
water passes through cation exchange units which convert the dissolved
salts to acids. Carbon dioxide is removed in a scrubbing tower and
the acids and most silica are removed in anion exchange units.
Finally the water passes through the mixed bed exchange units which
remove all the residual impurities to give a water of very high
purity. The final treated water has a conductivity of less than
0.1 dionic units and a silica content less than 0.01 parts per million.
This is essential to reduce the risk of boiler corrosion and of
damage to the turbine plant |
|
Condensers beneath
turbine |
|
|
| |
Switchgear & Electrical |
|
 |
|
Indoor substation
|
|
|
Each
machine has its own 13.8kV/3.3kV unit transformer, solidly connected
to the alternator terminals and rated at 10MVA. The 3.3kV system
is used to power the major auxiliaries. For starting there are two
10MVA station transformers drawing power from the 66kV system and
reducing the voltage to 3.3kV. Lower voltage supplies are taken
from the 3.3kV system through 3.3kV/415V auxiliary transformers |
The
site is connected to both the 66kV and 275kV systems. All generator
transformers are of 145MVA rating but the first three machines have
a voltage ratio of 13.8/66 and feed into the 66kV system whereas
generator transformer 4 has a 13.8/275 voltage ratio and feeds into
the 275kV grid system. |
The
66kV indoor substation contains 24 small oil volume circuit breakers
for switching :- Generators 1, 2 and 3 North Eastern Electricity
Board Feeders Two 145MVA transformers connecting with the 275kV
substation Bus couplers and Section switches. |
| |
Unit control
rooms |
|
There are two
control rooms situated on the operating floor. Each serves two units
and contains all the instrumentation and controls necessary to operate
the boilers, turbogenerators and auxiliary plant.
These include the displaying and recording of levels, pressures
and temperatures, associated with steam, water, flue gases and air,
along with the control and operation of the pulverising mills, boiler
draught plant and feed water systems, etc. |
 |
Associated
with each turbine, but outside the unit control rooms, are four
consoles housing the valves, turbovisory gear and instrumentation
used for starting up, running and closing down the turbines. |
| |
'A'
Station Unit control room |
|
| |
|
|
| |
B Station |
|
| Back to Top |
Boiler plant |
|
The two assisted circulation,
tangent tube boiler units have twin furnaces - superheater and reheater
- connected to a common steam and water drum. The boilers for Units
Nos. 7 and 8 were constructed by Clarke Chapman & Co. There
are five 40 tonne/hr Babcock & Wilcox pressure type IOE p.f.
mills per boiler driven by 450 h.p. 3.3kV 950 rpm motors.
Each mill has one primary air fan with an air capacity of 62,000
cu ft/min driven by a 540 h.p. 1480 rpm motor. Two mills feed each
furnace; the centre mill can feed either furnace as required.
The two 350,000 cu ft/min F.D. fans per boiler are driven by 590
rpm, 1370 h.p. motor and supply combustion air to the burners via
the two rotary air heaters which raise the air temperature to 271
°C. |
There are forty-eight
11,200 Ib/hr p.f. burners per boiler, arranged in groups of six
at each furnace corner. For lighting up there are 24 recirculating
tip fixed oil burners, push button operated from the unit control
panel. Each burner has a capacity of 3,300 Ibs/hr when operating
in high mode and 2,200lbs/hr in low mode.
The boiler gases leaving the economisers pass through rotary air
heaters, mechanical cellular dust extractors and electrostatic precipitators
to the I.D. fans and then to the flue. There are two 520,000 cu
ft/min two speed 740/590 rpm I.D. fans driven by 2000/1400
h.p. motors. The guaranteed efficiency of these boilers is 89.95
per cent on the gross calorific value of the fuel and have a maximum
continuous evaporative capacity of 2,350 kib/hr with a feed water
temperature of 260°C. |
The superheater
outlet steam conditions are 2400 p.s.i. at 269°C with reheating
at 594p.s-i.from 372 to 569°C. Four circulating pumps are provided
for each boiler, rated at 8.800 gal/min against a 136ft head with
water at 0.595 specific gravity.
The steam temperature at the superheater outlets is automatically
controlled by the operation of tilting burners in conjunction with
two spray type desuperheaters to regulate the final steam temperature
at 569°C ± 8°C between 70 and 100 maximum continuous
rating under specified operating conditions.
The spray desuperheaters are arranged for automatic bias control
and automatic operation at minimum burner angle.
The reheat outlet temperature is similarly controlled using the
reheat furnace tilting burners and emergency spray desuperheaters. |
 |
|
|
Babcox &
Wilcox 10E pulverising mill |
|
|
| |
Turbogenerators |
|
Units 7 and 8 turbogenerators,
manufactured by English Electric, are four cylinder, 3000 rpm, reheat
machines each with a design rating of 350MW. The high pressure (H.P.)
cylinder is of the reversed flow design, having a double casing
at the higher pressure end. The intermediate (1.P.) cylinder has
a partial double casing but is of straight flow construction. Two
low pressure (L.P.) cylinders, each of double flow construction,
exhaust to separate condensers. The turbine shafts are solidly connected
to the hydrogen cooled alternator. The alternator stator conductors
are directly cooled with water which is pumped around a closed system.
Steam from the H.P. steam chests passes through the H.P. cylinder
outer casing about half way along its length and enters the admission
belts of the inner cylinder before expanding successively through
eight stages of blading. The first five stages are housed within
the inner casing, the steam expanding towards the governor end.
The flow direction is then reversed and the steam passes over the
inner casing. Further expansion takes place through the three remaining
stages contained in the outer casing before the steam returns to
the boiler for reheating. Bled steam for No. 7 feedwater heater
is taken from the H . P. exhaust piping.
Steam enters the seven stage 1.P. cylinder from the reheater through
two interceptor valve chests. Two loop pipes from each chest are
connected to four steam admission pipes which pass through the outer
casing to the inner casing admission belt. |
The
steam expands successively through three stages of blading housed
in the inner casing and then through four stages contained in the
outer casing, before exhausting to the L.P. cylinders. Bled steam
for No. 6 feedwater heater is taken from after the third stage and
passed over the inner cylinder before leaving the turbine. Nos.
5 and 4 feedwater heaters receive their steam supply from after
stage five and the 1. P. cylinder exhaust.
Exhaust steam from the 1.P. cylinder enters the four flows of the
L.P.cylinders and expands through two impulse and three reaction
stages before exhausting to the condensers through 36in long last
row blades. Steam for No. 3 feedwater heater is bled from the LP.2
cylinder after the first stages, for No. 2 heater from L.P.I after
the second stages, and for No. 1 heater from both cylinders after
the third stages. The guaranteed steam and heat consumptions of
the turbogenerators are 6.3586 Ib/kWh and 7,525 BTU per kWh respectively.
Unit 8 turbogenerator |
Excitation
is provided by static rectifiers and an AC generator coupled to
the main shaft. The main feed pump is separately powered by a bled
steam turbine which forms an integral part of the feedheating system,
providing bled steam for Nos. 5 and 4 feedwater heaters.
The introduction of 36in long last row blades in the 'B' Station
turbo-generators was a significant advancement in turbine technology.
They were the first turbines in the world, rotating at 3000 rpm,
to have blades of this length. When the shaft is running at full
speed the velocity of the blade tip is 1780 ft/sec with each blade
exerting a centrifugal force of 112 tonnes at the root fastening
.
The 36in blades provide a much larger exhaust area than was previously
attainable, enabling turbines to be designed for greater power outputs.
This led directly to the present day single shaft, 3000 rpm turbines
with power outputs of up to 660MW. |
| |
|
| |
Condensing
& feedwater systems |
|

Condensers beneath turbine
|
Units
7 and 8 have twin-shell condensers with a total cooling surface
of 210,000 sq ft. Two 100 per cent duty extraction pumps are used,
each rated at 180,000 gal/hr and driven by 3.3kV, 800 h.p. motors
at 740 rpm. Three 50 per cent duty air pumps can each deal with
204lb of dry air per hour.
There are seven stages of feed heating consisting of three LP heaters,
one deaerator heater and three HP heaters. Feed water is heated
by bled steam from the turbine at a temperature of 252°C. The
three 50 per cent duty booster feed pumps, each rated at 2440 gal/min
and with a discharge pressure of 980 p.s.i., are driven by 2150
h.p. 1485 rpm motors.
The two 50 per cent duty standby/starting boiler feed pumps, each
rated at 276 / gal/min and having a discharge pressure of 2800 p.s.i.,
are driven by 4750 h.p. variable speed motors. |
The
100 per cent duty main feed pump is rated at 5,150 gal/min with
a suction pressure of 900 p.s.i. and a discharge pressure of 2800
p.s.i. It is driven by an 8100 h.p. English Electric bled steam
turbine. The 610 p.s.i. steam supply for this turbine is taken from
the cold reheat line at the main H.P. turbine exhaust. After passing
through the bled steam turbine it exhausts into the deaerator. A
bleed point is also incorporated on the bled steam turbine, supplying
steam for No. 5 h.p. feed water heater.
Control of the the boiler feedwater flow is affected by speed variations
of the standby/starting and main feed pumps. Feed regulating valves
are provided only to control the low flows experienced during starting
up and shutting down |
| |
| |
Circulating
Water System |
|
The arrangement of the 'B'
Station cooling water system is similar to that of 'A' Station.
Water is extracted from the head of the BIyth harbour tidal basin
and discharged to the sea off Cambois beach below low tide level.
The four vertical spindle, single entry, mixed flow C.W. pumps have
a head of 57ft.
They are driven through reduction gears by an 11 kV 3,250 h.p. 988
rpm motor to give an output, in each case, of 147,500gal/min at
185 rpm. |
The
reinforced concrete pump volutes are cast integral with the pump
foundations, which represented a new engineering development at
the time of the station's design.
Cooling water is circulated by a ring main and flows through the
condensers of each turbine at a rate of 155,000 gal/min. |
|
| |
Control Rooms |
|
| Control of the
two Units in the 'B' Station is from one central control room. A
central generator teaming desk is surrounded by a awtroj console
for the various electrical. systems, with the unit control and recorder
panels-around the perimeter of the room. Unit loading instructions
are received at the generator loading desk direct from the grid
control centre. |
’B’ station control room |
Synchronising,
generator switching ..and main electrical switching are carried
out from the electrical system control console. In each corner of
the room there is a suite of panels for the control of a single
unit comprising a control console and separate recorder panel.These
panels carry the controls and instrumentation necessary to start
up, run and close down the unit. |
| Back to Top |
Switchgear & Electrical |
|
| |
Each
machine has its own unit transformer connected solidly to the alternator
terminals to provide 11kV supplies. These step-down transformers
are rated at 30MVA for Units 7 and 8.
The 11 kV system is used to power the major auxiliaries. For starting
purposes there are two 30MVA station transformers drawing power
from the 66kV substation and reducing the voltage to 11kV.
Lower voltage supplies are provided by auxiliary transformers which
reduce the voltage to 3.3kV and 415 volts. |
This
substation contains eighteen air blast circuit breakers of 15.000MVA
rating, used for switching the infeeds and the feeders connecting
the station with the grid system.
Lower voltage supplies are provided by auxiliary transformers which
reduce the voltage to 3.3kV and 415 volts.
The generator transformers are rated at 400MVA. They have a voltage
ratio of 19.5/275kV and are connected, along with Unit 4 and the
two 66/275kV grid transformers, as infeeds to the 275kV substation.
This substation contains eighteen air blast circuit breakers of
15,000 MVA rating, used for switching the infeeds and the feeders
connecting the station with the grid system. |
| |
Ash and Dust
Disposal |
|
Ash is removed
by high pressure water jets from the boiler bottom ash hoppers and
transported down sluiceways at high velocity, via ash crushers to
the ash sump. Ash pumps then discharge the ash into settling ponds.
Dust from the precipitators and mechanical grit arresters is conveyed
by pneumatic gravity conveyors (air slides) to collector hoppers.
Each hopper forms an integral part of a dust pump which conveys
the dust by means of a scroll shaft to a mixing chamber.
Air from large capacity radial vane compressors enters the mixingchamber
via nozzles and transports the dust down pipelines to silos ajacent
to the coal stock.
Dry dust from the silos, conditioned by adding water to avoid dust
nuisance, is sent for sale or to the ash disposal sheme. This scheme
is being developed in three stages. The dust is compacted, landscaped
and covered with soil. Grass and other vegetation is then planted
to form a natural landscape feature |
|
|
Artists impression
of the ash disposal scheme |
Three-stage developement
|
| |
Main & Principal sub-contractors |
|
A' Station
BOILER PLANT
Boiler, superheater, reheater, airheater & pulverisers
Primary air fans
F.D. & I.D. fans
Precipitators
Ash handling plant
Dust handling plant
TURBOGENERATOR PLANT
Turbines, alternators, exciters,
condenser & feedwater heaters
Extraction pumps
Booster & boiler feed pumps
H.P. & L.P. pipework
|
Babcock &Wilcox
James Howden
Davidsons
Lodge Cottrell
Holden Engineers
Babcock & Wilcox
Metropolitan Vickers
Mather & Platt
Mather & Platt
Babcock &Wilcox
|
B' Station
BOILER PLANT
Main contractor
Superheater & reheater
Economiser
Boiler circulating pumps
P.A. fans
Pulverisers
F.D. & I.D. fans
Air heaters
Precipitators
Ash handling plant
Dust handling plant
TURBOGENERATOR PLANT
Turbines, alternators & exciters
Condensers
Booster, S/S & main feed pumps
Extraction pumps
H.P. pipework
L.P. pipework |
Clark Chapman
Superheater Co.
Green & Son
Hayward Tyier
Davidsons
Babcock & Wilcox
Davidsons
James Howden
Lodge Cottrell
Holden Engineers
Babcock & Wilcox
English Electric
Hick Hargreaves
Sulzer
Drysdale
John Thompson
Matthew Hall
|
|
| |
SWITCHGEAR & ELECTRICAL
66kV, 3.3kV & 415V switchgear :Reyrolle
Generator transformers: Ferranti |
|
SWITCHGEAR
& ELECTRICAL
275kV, 11 kV & 3.3kV switchgear:Reyrolle
415kV switchgear : M&C Switchgear Generator transformers Ferranti |
GENERAL SERVICES
Water treatment plant : Permutit
Circulating water pumps : Mather & Platt |
|
GENERAL
SERVICES
Water treatment plant: John Thompson (Kennicott)
Circulating water pumps : Gwynnes |
| |
Consulting Engineers
Main station, mechanical, electrical works Merz & McLellan
Circulating water & dockside work :-
Sir Alexander Gibb & Partners
Architects L.J. Couves & Partners
|
|
| Back to Top |
|
|